Install Flooring and Life Safety at Eye Clinic

VA Pacific Island HealthcareThis project consists of demolition of flooring, floor prep, installation and integration with existing system of fire suppression and controls, installation of flooring. This is a quick turn-around project of only 55 days from Notice to Proceed and requires coordination with other trades and contractors working in the same area. Material procurement and delivery were key items to maintain the schedule and budget. This project is on schedule to meet the July 31, 2015 completion date.

Pacific Islands Healthcare System, Honolulu, HI
VA261-12-D-0248 / VA261-14-J-2131, $71,875.00